DPW Projects (current as of July 10, 2014)
ProjectID Project Name Project Type Current Phase Council District Neighborhood Current Budget Start End Scope of Work
DPW381 ADA Access Ramps in CBD CDBG Funded Bid & Award B Central Business District $382,531.70 Q3 2014 Q3 2015 Installation of new ADA compliant  ramps in the CBD.
DPW438 Alabo St. (Chartres - Port) CDBG Funded Bid & Award E Holy Cross $366,666.67 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW003 Alcee Fortier Blvd Streetscape (Chef Menteur Hwy - Michoud Lagoon) CDBG Funded Complete E Village de Lest $500,000.00 15-Aug-13 A 30-Apr-14 A May include sidewalk or other pedestrian walkway improvements,  bikeways, traffic and pedestrian signage or signalization, landscaping,  lighting, or public art.
DPW004 Algiers (Traffic Signal) City Funded Complete C Algiers Point/McDonough/Behrman $3,395,804.37 02-Apr-12 A 21-Nov-13 A Traffic signal improvements
DPW343 Alvar St. (Chef Menteur - Higgins)  PTP Complete D Desire Area $677,527.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW342 Alvar St. (Higgins - Florida)  PTP Complete D Desire Dev $677,527.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW009 Audubon Blvd. (Willow St - S. Claiborne Ave) City Funded Complete A Audubon $9,032,725.13 18-Oct-10 A 26-Jun-12 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW363 Banks St. (Carrollton - St. Patrick)  PTP Complete A Mid-City $829,492.00 06-Nov-13 A 12-Mar-14 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW384 Baronne St. (Canal St - Calliope St.)  PTP Construction C Central Business District $1,392,336.00 24-Mar-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW354 Basin St. (Canal - N. Claiborne)  PTP Complete C Treme - Lafitte $1,878,613.00 22-Nov-13 A 03-Dec-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW010 Bayou Rd Streetscape (Broad St - Rocheblave St) CDBG Funded Construction D Seventh Ward $775,000.00 07-May-14 A Q4 2014 May include sidewalk or other pedestrian walkway improvements,  bikeways, traffic and pedestrian signage or signalization, landscaping,  lighting, or public art.
DPW011 Berkley Dr (Huntlee Canal - Woodland Dr) City Funded Complete C Old Aurora $8,266,148.96 14-Feb-11 A 15-Mar-12 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW012 Berkley Dr (Kabel Dr - Huntlee Dr), Somerset Dr (Berkley Dr - MacArthur Blvd) City Funded Bid & Award C Old Aurora $6,309,673.00 Q3 2014 Q2 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW364 Bienville St. (Jefferson Davis - Carrollton)  PTP Complete AB Mid-City $518,478.00 06-Nov-13 A 28-Feb-14 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW313 Broad and Washington Streetscape (S. Broad (Fourth - Louisiana) Washington (S. White - Dorgenois) CDBG Funded Construction B Broadmoor $357,563.16 10-Mar-14 A Q3 2014 May include sidewalk or other pedestrian walkway  improvements, bikeways, traffic and pedestrian signage or signalization,  landscaping, lighting, or public art.
DPW014 Broad St. and Lafitte St Streetscape (Bienville St - Orleans Ave)  CDBG Funded Bid & Award AB Tulane - Gravier $600,000.00 Q4 2014 Q1 2015 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW016 Broadmoor Streetscape (General Pershing from Broad St. to Miro St.) CDBG Funded Complete B Broadmoor $501,439.00 23-Aug-12 A 05-Feb-13 A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW361 Broadway St. (Fountainbleau - Leake)  PTP Complete AB Audubon $3,074,065.00 17-Apr-13 A 22-Aug-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW417 Burdette St. (Oleander - Forshey) CDBG Funded Bid & Award A Gert Town $31,262.50 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW367 Burgundy St. (Canal - Esplanade)  PTP Complete C French Quarter $1,382,353.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW385 Burgundy St. (Esplanade - Elysian Fields)  PTP Construction C Marigny & Bywater Neighborhoods $880,000.00 24-Mar-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW440 Caffin (Chartres - St. Claude Ave.) CDBG Funded Bid & Award E Holy Cross $366,666.67 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW018 Camp (Valmont - Jefferson), Chestnut/Coliseum (Valmont - Leontine), Leontine/Valmont (Mag-Prytania) City Funded Design B Uptown $304,383.02 Q4 2014 Q1 2015 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW019 Camp St. (Canal - US 90)  PTP Complete B Central Business District $1,274,264.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of trees, ADA  ramps and bike lane signage & striping.
DPW199 Camp St. (Louisiana Ave - Washington Ave) City Funded Design B Touro $138,314.00 Q4 2015 Q2 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW020 Canal Blvd. Reconstruction (Robert E. Lee Blvd - Amethyst St.) City Funded Design D Lakeshore-LakeVista $239,749.31 Q1 2016 Q1 2017 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW023 Carondelet St. (Canal St - US 90)  PTP Complete B Central Business District $941,878.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable,installation of ADA  ramps.
DPW024 Carrollton Ave  (St. Charles - Claiborne US 90)  PTP Complete A Mid-City $3,439,548.00 11-Jan-10 A 14-Jul-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps and bikelane striping &  signage.
DPW027 Carrollton Ave & Palmetto / Washington Streetscapes  CDBG Funded Complete AB Gert Town $1,694,789.96 28-May-13 A 24-Jan-14 A An enhancement project that may include: New road striping, improved curbs,  gutters and sidewalks, improvements to drainage and catch basins, installation  of new landscaping and streetlights.
DPW025 Carrollton Ave (South) (I-10 - Claiborne US 90)  PTP Complete AB Mid-City $3,520,481.00 11-Jan-10 A 14-Jul-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, renewal & replacement of  sidewalks, installation of ADA ramps.
DPW234 Carrollton Intersection (S. Carrollton Ave. from I-10 - Palm St.)  CDBG Funded Complete AB Gert Town $325,698.10 28-May-13 A 24-Jan-14 A Traffic signal and roadway intersection improvements
DPW029 Cartier Ave  (Mirabeau Ave - Filmore Ave) City Funded Bid & Award D Filmore $183,932.00 Q2 2015 Q3 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
PWF074 Catchbasin/Manhole Repair  City Funded Complete ABCDE City Wide $6,690,207.00 30-Jun-08 A 08-Aug-10 A Repair of catchbasins and manholes damaged as a direct result of  post-Hurricane Katrina clean-up efforts.
DPW030 Catina (Mouton - Robert E Lee), Louisville (Filmore - Robert E Lee) City Funded Complete A Lakeview $5,886,402.24 22-Mar-10 A 10-Jan-11 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW439 Charters (Alabo - Caffin) CDBG Funded Bid & Award E Holy Cross $366,666.67 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW034 Cherokee St (Hampson St - Freret St) City Funded Bid & Award A East Carrollton $2,064,604.00 Q3 2014 Q1 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW365 City Park Ave. (Canal - Orleans)  PTP Complete A Mid-City $1,244,264.00 04-Mar-13 A 24-Jun-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW036 City Park Tad Gormley Parking Lots (Marconi - Stadium Dr.) City Funded Design A City Park $157,117.00 Q1 2015 Q2 2015 New parking area at Tad Gormley Stadium and expand parking area at Marconi  Drive.
DPW178 Claiborne (South) @ Toledano (Napoleon Ave - Martin  Luther King  Jr.) CDBG Funded Complete B Central City $2,174,840.31 16-May-12 A 04-Dec-13 A An enhancement project that may include: A new memorial commemorationg the  contributions of nine New Orleans Civil Rights Leaders, palm tree lined walkways  from Jackson Ave to Josephine St, Lighting and landscaping in the median from  Napoleon Ave to Jackson Ave, new streetlights complete with fixtures on which to  hang decorative banners.
DPW089 Claiborne Avenue Streetscape (Cleveland St. - Gravier St.) City Funded Complete B Central Business District $2,371,700.00 04-Jan-10 A 17-Sep-10 A Sidewalk and landscaping  improvements
DPW041 Common St. (Loyola Ave - S. Peters St)  PTP Complete B Central Business District $1,236,691.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bikelane signage &  striping
DPW377 Congress St. (Hayne - Madrid)  PTP Construction D Pontchartrain Park $487,964.00 06-Jan-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW378 Congress St. (Madrid - Chef Menteur)  PTP Construction D Gentilly Woods $1,476,057.00 06-Jan-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW382 CostCo Infrastructure Improvements  CDBG Funded Complete AB Gert Town $3,465,599.00 29-Apr-13 A 03-Oct-13 A An enhancement project that may include: Demolition of existing frontage  roads, installation of road grading, new road striping, improved curbs,  gutters and sidewalks, improvements to drainage and catch basins,   construction of a deceleration lane on Palmetto St, warning beacons at  the Pontchartrain Expressway exit from I-10, new traffic signal at Dixon St and  Dublin St., and installation of new landscaping and  streetlights.
DPW285 Countdown Timers - Downtown City Funded Design B Central Business District $1,319,146.00 Q1 2015 Q3 2015 Retrofit existing traditional  walk/stop pedestrian signals with countdown timers and adding new pedestrian  countdown signals in the Downtown area.
DPW250 Crowder Blvd (Dwyer Rd - US 90) Bikeway City Funded Complete E Read Blvd West $9,600.00 08-Dec-09 A 01-Jul-10 A Install new pavement markings and  signage
DPW368 Dauphine St. (Canal - Esplanade)  PTP Complete C French Quarter $1,322,195.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW420 De Armas (LB Landry - Berhman) CDBG Funded Bid & Award C Whitney $700,655.85 15-Sep-14* Q4 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW372 Decatur St. (St Louis - Dumaine)  PTP Complete C French Quarter $599,038.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW045 DeSaix Bridge over Bayou St. John  City Funded Planning AD City Park $0.00 TBD TBD Bridge reconstruction
DPW403 Downman Rd (Babylon - Odin)  PTP Construction D Pines Village $412,500.00 16-Jun-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW048 Downtown  Bike Rack Installation Project City Funded Design B Central Business District $8,550.00 Q4 2015 Q4 2015 Installation of bike racks in various  locations.
DPW392 Downtown Infrastructure Improvements (Dorsiere, Iberville, Julia St)  CDBG Funded Construction BC Central Business District $5,500,000.00 24-Jul-13 A Q3 2014 The scope of work in the French Quarter includes resurfacing Dorsiere St.  from Iberville to Canal streets, and Iberville St. from North Peters to North  Rampart streets with concrete. These additional infrastructure improvements will  include new Americans with Disabilities Act-compliant curb ramps, repairs to  damaged sidewalks and driveway aprons, drainage point repairs, new striping and  crosswalks, repairs to damaged street lights including conversion of  non-historic streetlights to LED lights, signage improvements, and improved  sanitation practices.   The scope of work in the CBD includes resurfacing Julia St. from Convention  Center Blvd. to Loyola Ave. with concrete. These additional infrastructure  improvements will include new sidewalks and driveway aprons, Americans with  Disabilities Act-compliant curb ramps, drainage point repairs, new striping and  crosswalks, signage improvements, and improved sanitation practices.
DPW287 Dr. Charles R. Drew Elementary - Safe Routes to School (K08-572) State ID 737-99-1024  City Funded Bid & Award CD Bywater $288,041.00 Q3 2014 Q4 2014 Construct curb extensions with ADA compliant ramps at 16  locations, countdown pedestrian signals at 6 locations, pavement markings for  crosswalks at 16 locations, and miscellaneous markings and signs all in the  immediate vicinity of the Dr. Charles R. Drew Elementary School.  State  Project No. 737-36-0015 and Federal Project No. SRS-3608 (504).
DPW321 Drain Point Repair Services  City Funded Complete ABCDE City Wide $10,321,870.85 22-Feb-10 A 01-Oct-11 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
DPW293 Drainage Master Plan Study  CDBG Funded Complete ABCDE City Wide $1,996,459.00 #N/A 30-Apr-12 A Conduct field investigations and survey of major drainage  facilities.  Review and update existing Geographic Information System (GIS)  data.  Review and assess current data management, develop model for  new system.  Develop standards and guidelines, and maintenance  procedures.
DPW411 Drexel (Short - S. Genois) CDBG Funded Construction A Gert Town $232,300.75 27-Jun-14 A Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW050 Earhart Blvd Segment I (Hamilton St - Fern St)  City Funded Complete AB Gert Town $17,091,601.40 30-Nov-09 A 10-Oct-11 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW329 Edgelake Court (Crowder Rd - Hayne Blvd) City Funded Complete E Little Woods $378,910.00 08-Apr-13 A 29-May-13 A Asphalt pavement, base repair and  curb replacement.
DPW421 Elmira (Park - Newton) CDBG Funded Bid & Award C McDonogh $700,655.85 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW052 Elysian Fields (Lakeshore Dr. - Gentilly Blvd. / US 90)  PTP Complete D Gentilly $1,597,583.00 20-Nov-09 A 12-Apr-12 A Rehabilitation of roadway by milling existing surface and overlay with new  asphalt, including pre-milling patching repairs as well as adjustment of utility  manholes, where applicable, removal & replacement of concrete roadway from  Lakeshore Dr. - Robert E Lee Blvd, removal & replacement of sidewalk,  installation of ADA ramps, bike lane striping & signange.
DPW314 Esperanza Charter School - Safe Routes to School (K09-886)  State ID 737-99-1024 City Funded Bid & Award A Mid-City $321,074.00 Q3 2014 Q4 2014 Construct 16 curb extensions, sidewalk repair, 2 bike  racks, pavement markings, countdown pedestrian signals and signs near the  Esperanza Charter School.  State Project No. 737-36-0022 and Federal  Project No. SRS-3609 (509).
DPW396 Esplanade Ave (Claiborne - N.Rampart) Bikeway  City Funded Complete CD Treme - Lafitte $13,000.00 22-Aug-13 A 16-Jan-14 A Install new pavement markings and  signage
DPW366 Esplanade Ave. (Moss - N. Claiborne)  PTP Complete CD Treme - Lafitte $3,019,171.00 04-Mar-13 A 24-Jun-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW369 Esplanade Ave. (N Rampart - N Peters)  PTP Complete C French Quarter $1,602,028.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW055 Filmore Ave (Bayou St. John - Elysian Fields Ave) City Funded Complete D Filmore $2,743,221.00 20-Nov-09 A 31-May-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalk, installation of ADA ramps, bike lane striping &  signage.
DPW352 Filmore Ave. (Marconi - Wisner)  PTP Complete A City Park $512,344.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW351 Filmore Ave. (West End - Canal)  PTP Complete A Lakeview $512,344.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW056 Filmore Bridge over Bayou St. John  City Funded Planning AD City Park $0.00 TBD TBD Bridge  reconstruction
DPW058 Fleur de Lis Phase II (Veterans Blvd - Harrison Ave) City Funded Complete A West End $15,736,194.41 10-Dec-09 A 04-Mar-11 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW059 Fleur de Lis Phase III (30th - Hammond Hwy) City Funded Design A West End $9,776,000.00 Q1 2015 Q3 2015 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW359 Fontainebleau Dr. (Broadway - Nashville)  PTP Complete AB Marlyville & Fontainbleau $439,152.00 23-Aug-13 A 06-Nov-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW413 Forshey (S. Carrollton Ave. - Fern) CDBG Funded Bid & Award A Gert Town $55,376.25 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW340 Forstall St. (Douglass St. - N. Claiborne)  PTP Complete E Lower Ninth Ward $677,527.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW266 Franklin Ave. ( I-610 - LA 46) Bikeway  City Funded Design CD St. Claude $0.00 Q3 2014 Q3 2014 Install  new pavement markings and signage
DPW350 Franklin Ave. (Filmore - Gentilly)  PTP Complete D Gentilly Terrace $1,451,625.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW063 Freret St Streetscape (Napoleon Ave  - Jefferson Ave) CDBG Funded Complete B Freret $1,500,000.00 04-Nov-13 A 12-Mar-14 A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW357 Freret St. (Louisiana - Jefferson)  PTP Complete B Freret $1,375,469.00 23-Aug-13 A 06-Nov-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW278 Galvez ( Elysian Fields - Orleans Ave ) Bikeway City Funded Design D Treme - Lafitte $0.00 Q3 2014 Q3 2014 Install new pavement markings and  signage
DPW066 Galvez (Poydras - Orleans Ave.)  PTP Complete ACD Mid-City $749,628.00 27-Feb-10 A 30-Jun-11 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW068 Gardena Dr (St. Bernard Ave - Paris Ave.) City Funded Planning D Filmore $194,100.00 Q4 2017 Q1 2018 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW389 General DeGaulle Dr (Woodland - Holiday)  PTP Design C Old Aurora $1,508,000.00 Q3 2014 Q4 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW054 General Meyer Ave Streetscape (Hendee St - Odeon Ave) CDBG Funded Design C Behrman $684,906.37 Q4 2014 Q2 2015 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW349 Gentilly Blvd. (Paris - Broad)  PTP Complete AD Fairgrounds $2,415,337.00 01-Jun-13 A 17-Oct-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW070 Gentilly Minor Streets - Caton (Gentilly Blvd. - Norman Mayer Ave.), Touro (Caton - Senate) CDBG Funded Complete D Dillard $639,910.00 16-Sep-13 A 23-Jan-14 A Improvements to various  minor streets, which may include reconstruction and/or milling and overlay.
DPW071 Gentilly Streetscape (Caton, Gentilly, Elysian Fields) CDBG Funded Complete D Dillard $700,000.00 18-Nov-13 A 27-Jun-14 A May include sidewalk or other pedestrian walkway improvements, bikeways, traffic  and pedestrian signage or signalization, landscaping, lighting, or public art.
DPW429 Georgia St. (Amazon - Gen DeGaulle) CDBG Funded Bid & Award C Tall Timbers - Brechtel $35,002.00 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW272 Girod St.  ( Loyola Ave - S. Peters St)  Bikeway City Funded Complete B Central Business District $7,000.00 22-Aug-13 A 22-Oct-13 A Install new pavement markings and  signage
DPW074 Girod St. (Loyola Ave - S. Peters St)  PTP Complete B Central Business District $870,959.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW075 Gordon (Chartres - St. Claude), Flood (Peters - St. Claude) City Funded Complete E Lower Ninth Ward $7,963,993.91 01-Apr-11 A 01-Jun-12 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW076 Gravier St (Galvez - Broad) City Funded Bid & Award B Tulane - Gravier $186,888.25 Q2 2015 Q3 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW077 Gravier St. (Loyola Ave - S. Peters St)  PTP Complete B Central Business District $585,378.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW081 Harrison Ave Bridge over Bayou St. John (Eastbound)  City Funded Complete AD City Park $35,000.00 06-Apr-10 A 03-Oct-11 A Bridge  reconstruction
DPW082 Harrison Ave Bridge over Bayou St. John (Westbound)  City Funded Complete AD City Park $0.00 06-Apr-10 A 03-Oct-11 A Bridge reconstruction
DPW083 Harrison Ave Streetscape (Canal St - Orleans Ave) CDBG Funded Construction A Lakeview $4,001,850.00 18-Mar-13 A Q3 2014 An enhancement project that may include: Additional trees and shrubbery, new  brick-paved sidewalks, additional lighting, fresh crosswalk markings, and  improved irrigation.
DPW253 Harrsion Ave ( West End Blvd- Orleans Canal) Bikeways City Funded Design A Lakeview $0.00 Q3 2014 Q4 2014 Install new pavement markings and  signage
DPW344 Hayne Blvd. (Press - Congress)  PTP Complete D Pontchartrain Park $480,958.00 16-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW424 Hendee (Mardi Gras - Ptolemy) CDBG Funded Bid & Award C Whitney $91,525.60 Q3 2014 Q3 2014 Rehabilitation of concrete pavement  including panel patching/replacements, clearing and sealing of joints, crack  sealing and curb repair. Additional improvements include sidewalk repair,  construction of ADA ramps, installation of high-visibility crosswalks and other  roadway striping.
DPW425 Hendee (Ptolemy - Opelousas) CDBG Funded Bid & Award C Whitney $700,655.85 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW085 Holiday Dr  (General Meyer Ave - MacArthur) City Funded Complete C Old Aurora $3,255,254.15 01-Jun-11 A 07-Feb-12 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW086 Holiday Dr (MacArthur - Behrman) City Funded Complete C Old Aurora $2,674,648.06 15-Nov-11 A 16-Feb-12 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW245 Holy Cross Roadway Improvements - Douglass St., Andry St., N. Peters St. CDBG Funded Complete E Lower Ninth Ward $1,560,778.83 11-Jan-10 A 12-Oct-10 A Improvements to various  minor streets, which may include reconstruction and/or milling and overlay.
DPW087 Homedale (Canal - West End), Center (33rd - Tacoma), Milne (Homedale - Florida), Walker (Marshal-Orl City Funded Design A Lakeview $260,855.00 Q2 2015 Q1 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW088 Howard Avenue Ext. (Loyola Ave  - LaSalle St) City Funded Design B Central Business District $1,481,951.40 Q1 2015 Q2 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW243 Huntlee Dr. (General  DeGaulle - Berkley Dr) City Funded Bid & Award C Old Aurora $117,876.00 Q1 2015 Q3 2015 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW404 Hurricane Issac Repairs  City Funded Complete ABCDE City Wide $1,042,859.17 12-Dec-13 A 30-May-14 A The project  will consist of restoring damaged concrete sidewalks, concrete driveways,  barrier curbs, mountable curbs, and surrounding earth displaced by fallen trees  and other disaster related occurrences within the City right of way as a result  of Hurricane Isaac.
DPW430 Idaho St. (Wabash - Gen DeGaulle) CDBG Funded Bid & Award C Tall Timbers - Brechtel $98,583.38 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW431 Illinois St. (Gen DeGaulle - Amazon) CDBG Funded Construction C Tall Timbers - Brechtel $56,082.13 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW315 International School of LA - Safe Routes to School State ID 737-99-1024 City Funded Bid & Award B Lower Garden District $280,867.00 Q3 2014 Q4 2014 Construct curb extensions with ADA compliant ramps at  various locations, install countdown pedestrian signals, pavement markings for  crosswalks at various locations, and miscellaneous markings and signs all in the  immediate vicinity of the International School of LA.  State Project No.  737-36-0019.
DPW090 Jackson Ave (Claiborne Ave - Galvez St) City Funded Bid & Award B Central City $170,008.00 Q1 2015 Q2 2015 Reconstruction of existing roadway,  including the replacement of affected utilities
DPW442 Jackson Ave. (S. Claborne - Tchopitoulas) CDBG Funded Planning B Central City, Lower Garden District, St. Thomas Dev $3,750,000.00 Q3 2015 Q2 2016 Scope of work includes 2" mill and overlay, some full depth patches, installation of ADA complaint curb ramps, sidewalks, and new striping.
DPW283 Jefferson Ave. (Caliborne - Tchoupitoulas ) Bikeway City Funded Design A Audubon $0.00 Q3 2014 Q3 2014 Install new pavement markings and  signage
DPW092 Johnson St (Jefferson - Claiborne), Melodia (Claiborne - S. Johnson), Octavia (Freret - Claiborne) City Funded Bid & Award A Audubon $346,480.00 Q4 2015 Q3 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW094 Lafitte Greenway Bicycle/Pedestrian Path - (N. Alexander- Basin)  CDBG Funded Construction CD Treme - Lafitte $12,772,000.00 20-Mar-14 A Q1 2015 Includes sidewalk and pedestrian  walkway improvements, bikeways, traffic and pedestrian signage, landscaping,  lighting, and public art.
DPW432 Laharpe St. (St. Bernard Ave - N. Claiborne) CDBG Funded Construction D Seventh Ward $77,149.88 10-Jul-14 A Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW097 Lake Forest Ave. Traffic Improvements  (Lake Forest at Bullard) City Funded Planning E New Orleans East $0.00 Q3 2015 Q4 2015 Roundabout Evaluation
DPW096 Lake Forest Blvd. Widening (Eastover Dr - I-510) City Funded Design E Read Blvd East $160,815.00 Q1 2015 Q1 2016 Widening of existing roadway,  including the replacement of affected utilities.
DPW098 Lakefront/Holy Cross Traffic Signals City Funded Complete A Holy Cross $7,067,181.21 17-Jan-12 A 08-Mar-13 A Traffic signal  improvements
DPW428 Lamarque (LB Landry - Sumner) CDBG Funded Bid & Award C Whitney $207,688.25 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW100 LaSalle St (Poydras - Tulane Ave US 61)  PTP Complete B Uptown $741,349.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bike lane striping &  signage.
DPW101 LeBoeuf (Patterson - Opelousas), Sumner (Newton - Opelousas), Slidell (Whitney - Sumner) City Funded Complete C U.S. Naval Base $5,970,079.66 07-Feb-11 A 22-Dec-11 A Reconstruction of existing roadway, including the  replacement of affected utilities.
DPW102 Leon C. Simon Dr (London Canal - Elysian Fields Ave)  PTP Complete D Lake Terrace and Oaks $1,208,379.00 20-Nov-09 A 18-Apr-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA ramps,  bike lane striping & signage.
DPW360 Leonidas St. (Palmetto - Earhart)  PTP Complete A Hollygrove $426,936.00 17-Apr-13 A 22-Aug-13 A Removal  and replacement of the sidewalk intersections for the installation of the  compliant ADA ramps and the installation of the ADA ramps in the  medians.
DPW282 Louisiana Ave ( St. Charles - Magazine) Bikeway City Funded Design B Touro $0.00 Q3 2014 Q3 2014 Install new pavement markings and  signage
DPW292 Lower Ninth Ward Pilot Streets - Make It Right City Funded Complete E Lower Ninth Ward $434,008.00 11-Jun-12 A 24-Sep-12 A Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW106 Lower Ninth Ward Streetscape Phase I (N. Claiborne - Andry to Lamanche)(St. Claude-Bridge to Egania) CDBG Funded Complete E Lower Ninth Ward $1,900,000.00 01-Jun-12 A 18-Nov-12 A An enhancement project that may include: Sidewalk  and ADA-compliant curb ramps, landscaping, lighting, public art space,  and minor utility modifications and improvements.
DPW393 Lower Ninth Ward Streetscape Phase II (N. Claiborne -  Lamanche - Tennessee) CDBG Funded Design E Lower Ninth Ward $655,748.05 Q4 2014 Q1 2015 An enhancement project that may include: Sidewalk  and ADA-compliant curb ramps, landscaping, lighting, public art space,  and minor utility modifications and improvements.
DPW108 Loyola Ave. (Canal St. - US 90)  PTP Complete B Central Business District $3,584,538.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bike lane striping &  signage.
DPW399 MacArthur Blvd (Gen deGaulle - Kabel)  PTP Design C Old Aurora $1,312,211.73 Q4 2014 Q1 2015 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW113 Magazine St. (Canal - US 90)  PTP Complete B Central Business District $1,104,237.00 03-Nov-09 A 25-Aug-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bike lane striping &  signage.
DPW110 Magazine St. (St. Joseph St - Calliope St) City Funded Complete B Central Business District $4,941,907.88 29-Jun-09 A 13-May-10 A Sidewalk and landscaping  improvements
DPW114 Magazine St. (US 90B - Nashville)  PTP Complete AB Uptown $3,373,617.00 04-Jan-11 A 10-Nov-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA ramps  including  street names and bikelane striping & signage, removal &  replacement of sidewalks.
DPW112 Magazine St. Phase I (Nashville Ave - Calhoun St) City Funded Design A Audubon $4,776,624.00 Q1 2015 Q1 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW111 Magazine St. Phase II (Calhoun - Leake Ave) City Funded Design A Audubon $7,039,708.00 Q3 2015 Q3 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW391 Magnolia Converted Ped Bridge City Funded Planning A Bayou St. John $844,400.00 Q1 2016 Q2 2016 Bridge reconstruction
DPW419 Magnolia Market Place Streetscape CDBG Funded Bid & Award B Central City $110,000.00 Q3 2014 Q3 2014 An enhancement project that may include: Sidewalk and ADA-compliant curb ramps, landscaping, lighting, public art space, and minor utility modifications and improvements.
DPW249 Marconi Blvd. (Robert E. Lee - Norfolk Southern Railroad) Bikeways  City Funded Complete AC City Park $24,750.00 08-Dec-09 A 16-Jun-10 A Install new pavement markings and  signage
DPW118 Martin Bridge over Morrison City Funded Complete E Little Woods $1,188,700.00 02-Nov-11 A 28-Jun-12 A Bridge  reconstruction
DPW263 Martin Luther King  Blvd ( Caliborne Ave - Broad St ) Bikeway City Funded Complete B B. W. Cooper $24,850.00 22-Aug-13 A 21-Oct-13 A Install new pavement markings and  signage
DPW395 Martin Luther King Blvd (Washington - Earhart) Bikeway City Funded Complete B Gert Town $2,402.80 22-Aug-13 A 17-Dec-13 A Install new pavement markings and  signage
DPW346 Mayo Rd. (Hayne - Morrison)  PTP Complete E Little Woods $601,198.00 16-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW347 Mayo Rd. (Morrison - I-10)  PTP Complete E Little Woods $360,719.00 03-Aug-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW397 Mercedes St (MacArthur - Herschel)  PTP Complete C Behrman $232,000.00 08-Apr-14 A 27-Jun-14 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW120 Michoud Blvd (Chef Menteur Blvd - Dwyer Rd) City Funded Bid & Award E Village de Lest $221,228.20 Q3 2015 Q4 2015 Removal of existing roadways and replace with  new hot mix asphalt roadways including new concrete curb and gutter bottom,  rehabilitation of water and drain lines, constructing driveways, sidewalks and  handicap ramps, and all work incidental to the project as shown on the plans or  as directed by the Engineer in the field.
DPW142 Michoud Front Door Infrastructure Improvements (Old Gentilly Road from I-510 - Chef Menteur Highway) CDBG Funded Bid & Award E Viavant $6,729,848.00 Q4 2014 Q3 2015 An enhancement project that may  include: Construction of both new asphalt, and concrete roadways and appropriate  striping, repair of existing roadways, landscaping, install and improved  lighting, improved drainage, and intersection improvements at  Chef Menteur and Almonaster Blvd.
DPW128 Mirabeau Ave (Bayou St. John - Elysian Fields Ave)  PTP Complete D Filmore $2,950,864.00 20-Nov-09 A 02-May-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalk, installation of ADA ramps, bike lane striping &  signage.
DPW277 Miro St ( Elysian Fields Ave - Orleans Ave) Bikeway City Funded Complete D Seventh Ward $24,450.00 22-Aug-13 A 15-Oct-13 A Install new pavement markings and  signage
DPW129 Miro St (Elysian Fields Ave - Orleans Ave)  PTP Complete ACD Mid-City $978,426.00 04-Jan-10 A 16-Jun-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW345 Morrison Rd. (Lamb - Mayo)  PTP Complete E Little Woods $961,917.00 16-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW373 N Peters St. (Canal - St Louis)  PTP Complete C French Quarter $1,200,219.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW067 N. Galvez  St (Elysian Fields Ave  - Almonaster Ave )  City Funded Bid & Award CD St. Roch $196,400.00 Q1 2015 Q3 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW289 N. Galvez (Orleans Ave. - Poydras)  PTP Complete AB Mid-City $3,309,167.00 04-Jan-10 A 16-Jun-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable  installation of ADA  ramps.
DPW130 N. Galvez St (Tennessee St  - Delery St) City Funded Bid & Award E Lower Ninth Ward $391,800.00 Q4 2014 Q1 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW436 N. Robertson (Columbus - St. Bernard Ave.) CDBG Funded Construction D Seventh Ward $81,400.00 10-Jul-14 A Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW435 N. Robertson (Esplanade Ave. - Columbus) CDBG Funded Construction D Seventh Ward $109,670.00 10-Jul-14 A Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW434 N. Villiere St. (Columbus - Annette) CDBG Funded Construction D Seventh Ward $111,809.50 10-Jul-14 A Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW433 N. Villiere St. (Esplanade Ave. - Columbus) CDBG Funded Construction D Seventh Ward $84,609.25 10-Jul-14 A Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW238 Napoleon, Broad and Fontainebleau Intersection Design CDBG Funded Complete B Broadmoor $250,000.00 #N/A 07-Aug-12 A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW290 Napoleon-Freret Roadway Improvements (Clara St. (Napoleon - Cadiz), Jena (Clara - S. Claiborne)) CDBG Funded Complete B Freret $754,537.24 11-Feb-11 A 14-Oct-11 A Improvements to various minor streets,  which may include reconstruction and/or milling and overlay.
DPW284 Nashville Ave (Caliborne US 90 - Tchoupitoulas) Bikeway City Funded Complete A Audubon $14,450.00 22-Aug-13 A 04-Nov-13 A Install new pavement markings and  signage
DPW131 Nashville Ave (Claiborne US 90 - Magazine St ) (Magazine St - Tchoupitoulas St)  PTP Complete A Uptown $5,429,536.00 09-Nov-09 A 16-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & relpacement of  sidewalks &  installation of ADA ramps.
DPW358 Nashville Ave. (S.Claiborne - Fountainbleau)  PTP Complete A Marlyville & Fontainbleau $622,132.00 23-Aug-13 A 06-Nov-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW279 Navarre Ave ( Canal Blvd - Marconi Dr) Bikeway City Funded Complete A City Park $7,200.00 22-Aug-13 A 21-Oct-13 A Install new pavement markings and  signage
DPW132 Navarre Ave. (Canal Blvd. - Marconi Dr)  PTP Complete A Lakeview $808,592.00 04-Jan-10 A 16-Nov-10 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW239 New Orleans East Streetscape Improvements (Read Blvd, Lakeforest Blvd, Crowder Rd) CDBG Funded Complete E New Orleans East $3,000,000.00 19-Apr-12 A 14-Jun-13 A An enhancement project that may  include: New sidewalks along Lake Forest Blvd, with access to the New Orleans  East Regional Library and Joe Brown Park, new seating and trach receptacles at a  small park at the corner of Lake Forest and Wright Rd, installing a new walking  path on Lake Forest Blvd from Wright Rd to Read Blvd, Adding about 140  additional lights and more that 30 new trees,  and developing a dedicated bike lane on Read Blvd,  Crowder Blvd and Lake Forest Blvd.
DPW137 New Orleans Museum District Enhancement City Funded Construction B Central Business District $499,141.73 07-Jan-14 A Q3 2014 An enhancement project that may  include: Removal and replacement of concrete curbs, walkways, gutters, and  driveways, installation of new brick sidewalks, removal and replacement of  asphalt pavement, adjustment of manholes, catch basins and in-ground utility bases, installation of new ADA-compliant  ramps at corners, planting new plants. trees and tree  grates.
DPW390 Newton St (Whitney - Behrman)  PTP Design C Whitney $1,059,700.00 Q3 2014 Q4 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW387 Newton St (Whitney - Teche)  PTP Complete C Whitney $913,200.00 08-Apr-14 A 27-Jun-14 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW402 North Galvez (Orleans - Elysian Fields Ave)  PTP Construction D Seventh Ward $2,777,300.00 16-Jun-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW443 Old Poydras St. (S. Dorgenois - S. Galvez) CDBG Funded Planning B Tulane-Gravier $1,000,000.00 Q3 2015 Q2 2016 Scope of work includes removing and  replacing the existing roadway, resurfacing and installation of ADA  complaint curb ramps.
DPW144 Old Spanish Trail (Nighthart St - Sherwood Dr) City Funded Bid & Award E Read Blvd East $104,316.00 Q1 2016 Q2 2016 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW415 Oleander St. (Short - Burdette) CDBG Funded Bid & Award A Gert Town $96,955.00 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW322 Opelousas Street Extension (Behrman Avenue to O'Bannon St.) CDBG Funded Complete C Algiers Point $2,060,363.11 11-Feb-11 A 27-Jun-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable.
DPW140 Oretha Castle Haley Blvd Streetscape (St. Andrew St. - Calliope St.) CDBG Funded Design B Central City $968,540.30 Q1 2015 Q2 2015 An enhancement project that may  include: Removal of the median between Felicity St and Martin Luther King Blvd,  larger pedestrian crossings/medians at intersections, installation of new  ADA-compliant ramp curbs, repairs to damaged sidewalks, conversion of the  roadway from two travel lanes  and parking lane into a parking lane, bicycle lae  and travel lane in each direction.
DPW145 Orleans Ave. (N. Claiborne Ave - City Park Ave.)  PTP Complete A Mid-City $4,437,504.00 04-Jan-10 A 01-Oct-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW414 Orpheus Ct. (S. Carrollton Ave. - Short) CDBG Funded Bid & Award A Gert Town $18,570.00 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW388 Pace Blvd (Gen Meyer Ave - Wall Blvd)  PTP Complete C Behrman $1,305,000.00 08-Apr-14 A 27-Jun-14 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW147 Paris Ave. (I-610 - Mirabeau Ave)  PTP Complete D St. Bernard Area $742,125.00 20-Nov-09 A 16-Apr-12 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, Concrete panel replacement,  removal & replacement of sidewalks, installation of ADA ramps, bike lane  striping & signage.
DPW150 Park Island Bridge over Bayou St. John  City Funded Complete AD Filmore $88,766.15 08-Dec-09 A 01-Jun-11 A Bridge  reconstruction
PWF006 Patching Repairs - City Park FEMA Phase I Complete A City Park $250,687.19 17-May-10 A 22-Nov-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF013 Patching Repairs - Filmore FEMA Phase I Complete D Filmore $1,933,364.98 15-Feb-10 A 03-Aug-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF018 Patching Repairs - Gentilly Woods FEMA Phase I Complete D Gentilly Woods $439,126.74 06-Jul-10 A 10-Sep-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF023 Patching Repairs - Lake Terrace & Oaks FEMA Phase I Complete D Lake Terrace and Oaks $713,661.32 30-Aug-10 A 15-Dec-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF024 Patching Repairs - Lakeshore - Lake Vista FEMA Phase I Complete D Lakeshore-LakeVista $820,539.58 15-Mar-10 A 27-Aug-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF025 Patching Repairs - Lakeview FEMA Phase I Complete A Lakeview $6,813,271.55 14-Apr-09 A 22-Jul-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF026 Patching Repairs - Lakewood FEMA Phase I Complete A Lakewood $290,934.76 17-Aug-09 A 03-Jun-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF030 Patching Repairs - Lower Ninth Ward FEMA Phase I Complete E Lower Ninth Ward $2,174,266.00 23-Mar-09 A 04-Feb-11 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF032 Patching Repairs - Marlyville & Fontainebleau  FEMA Phase I Complete AB Marlyville & Fontainbleau $5,561,714.45 14-Jun-10 A 10-Dec-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF034 Patching Repairs - Milan & Touro Neighborhoods FEMA Phase I Complete B Milan & Touro Neighborhoods $634,253.01 05-Apr-10 A 15-Jul-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF035 Patching Repairs - Milneburg FEMA Phase I Complete D Milneburg $3,154,723.47 02-Oct-09 A 23-Jul-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF036 Patching Repairs - Navarre FEMA Phase I Complete A Navarre $791,313.16 23-Aug-10 A 07-Jan-11 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF039 Patching Repairs - Pines Village FEMA Phase I Complete D Pines Village $988,139.95 26-Apr-10 A 20-Jul-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF043 Patching Repairs - Read Blvd West FEMA Phase I Complete E Read Blvd West $2,235,635.64 03-Aug-09 A 12-May-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF049 Patching Repairs - Treme - Lafitte  FEMA Phase I Complete CD Treme - Lafitte $2,318,252.27 01-Dec-09 A 17-May-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF051 Patching Repairs - Uptown & West Riverside  FEMA Phase I Complete AB Uptown & West Riverside $727,106.35 02-Nov-09 A 06-May-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
PWF053 Patching Repairs - West End FEMA Phase I Complete A West End $1,789,465.06 26-Oct-09 A 10-Dec-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris removal.
DPW323 Patterson Drive Extension Phase 1 (Hendee St. to Heerman St) City Funded Complete C Old Aurora $3,464,242.49 03-Dec-12 A 13-May-13 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable.
DPW380 Patterson Drive Extension Phase 2 Heerman St to O'Bannon St.) City Funded Bid & Award C Old Aurora $860,882.00 Q3 2014 Q4 2014 Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable.
DPW158 Poydras St (Carondelet St - Camp St)  PTP Complete B Central Business District $129,243.00 03-Nov-09 A 25-Aug-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, lakebound, Camp- St Charles  only.
DPW159 Poydras St (LaSalle St  - Loyola Ave)  PTP Complete B Central Business District $106,042.00 03-Nov-09 A 25-Aug-10 A Installation of compliant ADA ramps, Bike lane striping  & signage.
DPW255 Press Dr( US 90 - Robert E Lee Blvd ) Bikeway City Funded Complete D Gentilly Woods $0.00 08-Dec-09 A 16-Jun-10 A Install new pavement markings and  signage
DPW233 Press Drive Streetscape  (Chef - Leon C Simon) CDBG Funded Complete D Pontchartrain Park $245,996.10 19-Apr-12 A 17-Dec-13 A An enhancement project that may include: Planting more  than 250 trees and over 533 shrubs on the median from Chef Menteur Hwy to Leon  C. Simon Blvd, installing neighborhood signage at Press Dr, as well as signs  denoting the Gentilly Woods and Pontchartrain Park Neighborhoods.
PWF159 Recovery Program - Algiers Point, Behrman, McDonagh, Whitney FEMA Phase II Design C Algiers Point/McDonough/Behrman/Whitney $4,126,037.71 Q2 2017 Q2 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF128 Recovery Program - Audubon FEMA Phase II Design A Audubon $3,051,692.60 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF142 Recovery Program - B.W. Cooper FEMA Phase II Design B B. W. Cooper $4,652,028.60 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF140 Recovery Program - Bayou St. John/Fairgrounds  FEMA Phase II Design AD Fairgrounds/Bayou St. John $4,453,235.57 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF165 Recovery Program - Black Pearl FEMA Phase II Design A Black Pearl $2,389,538.87 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF100 Recovery Program - Broadmoor  FEMA Phase II Design AB Broadmoor $6,732,603.09 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF120 Recovery Program - Bywater/Marigny FEMA Phase II Design C Marigny & Bywater Neighborhoods $876,452.69 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF139 Recovery Program - Central City FEMA Phase II Design B Central City $9,951,917.04 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF126 Recovery Program - City Park FEMA Phase II Design A City Park $802,606.31 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF136 Recovery Program - Desire Area Development FEMA Phase II Design D Desire Area $3,403,558.64 Q1 2016 Q1 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF123 Recovery Program - Dillard FEMA Phase II Design D Dillard $3,528,899.20 Q3 2015 Q3 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF138 Recovery Program - Dixon FEMA Phase II Design A Dixon $3,533,495.98 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF164 Recovery Program - East Carrollton FEMA Phase II Design A East Carrollton $8,383,435.07 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF141 Recovery Program - East Riverside, Garden District, Irish Channel, St. Thomas Dev FEMA Phase II Design B East Riverside, Garden District, Irish Channel, St Thomas Dev $9,114,704.34 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF112 Recovery Program - Filmore Quadrant 1 FEMA Phase II Design D Filmore $12,885,267.88 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF113 Recovery Program - Filmore Quadrant 2 FEMA Phase II Design D Filmore $3,291,318.35 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF146 Recovery Program - Fisher Development FEMA Phase II Design C Fisher Development $17,630.27 Q1 2017 Q1 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF119 Recovery Program - Florida Area/Florida Development FEMA Phase II Design D Florida Area/Fischer Dev./Florida Dev. $4,461,861.45 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF127 Recovery Program - Freret FEMA Phase II Design B Freret $1,607,052.38 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF137 Recovery Program - Gentilly Terrace FEMA Phase II Design D Gentilly Terrace $14,946,092.36 Q1 2016 Q1 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF133 Recovery Program - Gentilly Woods FEMA Phase II Design D Gentilly Woods $3,455,390.44 Q4 2015 Q4 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF151 Recovery Program - Gert Town  FEMA Phase II Design AB Gert Town $5,218,756.82 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF143 Recovery Program - Hollygrove and Leonidas FEMA Phase II Design A Hollygrove and Leonidas $14,247,678.18 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF129 Recovery Program - Holy Cross - Part 1  FEMA Phase II Bid & Award CD Holy Cross $2,996,842.44 Q3 2014 Q4 2014 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF170 Recovery Program - Holy Cross - Part 2  FEMA Phase II Bid & Award CD Holy Cross $963,567.95 Q3 2014 Q4 2014 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF131 Recovery Program - Iberville/ Tulane Gravier  FEMA Phase II Design BC Tulane/Gravier/Iberville Neighborhoods $4,147,313.22 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF125 Recovery Program - Lake Terrace & Oaks FEMA Phase II Design D Lake Terrace and Oaks $6,433,561.03 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF168 Recovery Program - Lake Vista FEMA Phase II Design D Lakeshore-LakeVista $8,920,792.03 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF107 Recovery Program - Lakeshore FEMA Phase II Design D Lakeshore-LakeVista $6,031,207.99 Q4 2015 Q4 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF102 Recovery Program - Lakeview - Vicksburg St. Demonstration FEMA Phase II Complete A Lakeview $250,000.00 01-Oct-12 A 03-Dec-12 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF172 Recovery Program - Lakeview (Pavement Only Quad 1) FEMA Phase II Design A Lakeview $2,702,851.65 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF103 Recovery Program - Lakeview Quadrant 1 FEMA Phase II Design A Lakeview $14,699,415.46 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF104 Recovery Program - Lakeview Quadrant 2 FEMA Phase II Design A Lakeview $4,051,528.30 Q3 2015 Q3 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF108 Recovery Program - Lakewood FEMA Phase II Design A Lakewood $3,392,692.24 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF115 Recovery Program - Little Woods  FEMA Phase II Design DE Little Woods $1,893,544.33 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF156 Recovery Program - Lizardi St FEMA Phase II Complete E Lower Ninth Ward $947,491.60 08-Apr-13 A 17-Jun-13 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF106 Recovery Program - Lower Garden District/CBD  FEMA Phase II Design BC Lower Garden District/Central Business District $1,315,523.82 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF096 Recovery Program - Lower Ninth Ward (Pavement Only - Quad 1) FEMA Phase II Design E Lower Ninth Ward $1,824,789.58 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF157 Recovery Program - Lower Ninth Ward (Pavement Only - Quad 2) FEMA Phase II Design E Lower Ninth Ward $6,941,623.84 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF171 Recovery Program - Lower Ninth Ward (Pavement Only - Quad 3) FEMA Phase II Design E Lower Ninth Ward $4,257,842.35 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF080 Recovery Program - Lower Ninth Ward Phase II (Deslonde and Flood) FEMA Phase II Complete E Lower Ninth Ward $4,794,701.22 25-Mar-13 A 25-Mar-14 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF093 Recovery Program - Lower Ninth Ward Quadrant 1 FEMA Phase II Design E Lower Ninth Ward $10,488,630.78 Q4 2015 Q4 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF094 Recovery Program - Lower Ninth Ward Quadrant 2 FEMA Phase II Design E Lower Ninth Ward $12,362,392.00 Q4 2015 Q4 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF095 Recovery Program - Lower Ninth Ward Quadrant 3 FEMA Phase II Design E Lower Ninth Ward $9,502,046.21 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF148 Recovery Program - Marlyville-Fontainebleau  FEMA Phase II Design AB Marlyville & Fontainbleau $13,135,050.90 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF117 Recovery Program - Mid City  FEMA Phase II Design AB Mid-City $9,212,149.46 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF167 Recovery Program - Milan FEMA Phase II Design B Milan $2,173,479.85 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF101 Recovery Program - Milneburg FEMA Phase II Design D Milneburg $3,286,959.44 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF114 Recovery Program - Navarre FEMA Phase II Design A Navarre $1,624,500.07 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF145 Recovery Program - Old Aurora, Tall Timbers-Brechtel, U.S. Naval Base FEMA Phase II Design C Old Aurora/Tall Timbers - Brechtel/U.S. Naval Base $1,291,409.17 Q1 2017 Q1 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF135 Recovery Program - Pines Village FEMA Phase II Design D Pines Village $3,894,656.12 Q1 2016 Q1 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF110 Recovery Program - Plum Orchard FEMA Phase II Design E Plum Orchard $6,198,578.80 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF109 Recovery Program - Pontchartrain Park FEMA Phase II Design D Pontchartrain Park $10,576,346.65 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF105 Recovery Program - Read Blvd East FEMA Phase II Design E Read Blvd East $14,608,649.81 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF134 Recovery Program - Read Blvd West FEMA Phase II Design E Read Blvd West $7,065,118.55 Q1 2016 Q1 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF130 Recovery Program - Seventh Ward  FEMA Phase II Design CD Seventh Ward $4,121,789.41 Q2 2016 Q2 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF121 Recovery Program - St. Anthony Quadrant 1 FEMA Phase II Design D St. Anthony $9,775,135.73 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF122 Recovery Program - St. Anthony Quadrant 2 FEMA Phase II Design D St. Anthony $8,182,137.46 Q3 2015 Q3 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF124 Recovery Program - St. Bernard FEMA Phase II Design D St. Bernard Area $2,038,882.50 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF099 Recovery Program - St. Claude (Paving Only)  FEMA Phase II Design CD St. Claude $8,263,804.92 Q4 2014 Q4 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF082 Recovery Program - St. Claude Phase II Group 1  FEMA Phase II Construction CD St. Claude $3,485,554.02 24-Feb-14 A Q4 2014 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF097 Recovery Program - St. Claude Quadrant 1  FEMA Phase II Design CD St. Claude $2,708,760.58 Q4 2015 Q4 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF158 Recovery Program - St. Claude Quadrant 1- Feliciana St  FEMA Phase II Complete CD St. Claude $182,436.25 04-Mar-13 A 23-May-13 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF098 Recovery Program - St. Claude Quadrant 2  FEMA Phase II Design CD St. Claude $5,633,528.96 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF111 Recovery Program - St. Roch  FEMA Phase II Design CD St. Roch $7,557,268.34 Q2 2015 Q2 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF118 Recovery Program - Touro FEMA Phase II Bid & Award B Touro $756,976.46 Q3 2014 Q3 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF150 Recovery Program - Treme - Lafitte  FEMA Phase II Design CD Treme - Lafitte $5,207,880.84 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF144 Recovery Program - Uptown  FEMA Phase II Design AB Uptown $3,845,318.42 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF155 Recovery Program - Venetian Isles FEMA Phase II Construction E Venetian Isles $1,411,809.52 07-Jul-14 A Q4 2014 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF166 Recovery Program - Viavant / Lake Catherine FEMA Phase II Design E Viavant, Lake Catherine, Venetian Isles $4,537,782.11 Q3 2015 Q3 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF169 Recovery Program - Village De L'Est FEMA Phase II Design E Village de Lest $7,954,132.71 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF116 Recovery Program - West End FEMA Phase II Design A West End $13,516,151.32 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF149 Recovery Program - West Lake Forest FEMA Phase II Design E West Lake Forest $713,470.97 Q1 2015 Q1 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
PWF152 Recovery Program - West Riverside  FEMA Phase II Design AB West Riverside $975,818.27 Q3 2016 Q3 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving.
DPW320 Reinventing the Crescent Infrastructure Imp. N Peters(St Philip-St Ferdinand)Chartres(Piety-Gallier) CDBG Funded Complete C Marigny & Bywater Neighborhoods $816,507.91 19-Oct-09 A 03-Jun-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of Sidewalks  & ADA ramps.
DPW437 Reynes St. (St. Claude Ave. - Douglas) CDBG Funded Bid & Award E Holy Cross $146,037.38 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW254 Robert E Lee Blvd ( St. Bernard Ave- Paris Ave) Bikeway  City Funded Complete AD Filmore $13,300.00 13-Jan-14 A 17-Jan-14 A Install new pavement markings and  signage
DPW353 Robert E Lee Blvd. (Elysian Fields - Franklin)  PTP Complete D Milneburg $1,036,904.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW317 Robert E. Lee (Paris to Pratt) City Funded Complete A Filmore $3,168,364.33 02-Nov-09 A 05-May-10 A Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW241 Robert E. Lee Blvd (Perlita Dr - Chatham Dr) and Paris Ave. (Robert E. Lee - Aviators) Streetscape CDBG Funded Complete D Filmore $749,995.00 12-Aug-13 A 17-Apr-14 A An enhancement project that may include: Installation of new sidewalks and  drivewa aprons, installation of ADA-complaint ramps at sidewalk corners, new  bicycle lane striping, fresh crosswalk and pavement striping, new landscaping  including planting of about 75 trees, new neighborhood signage and lighting, and  improved drainage.
DPW173 Robert E. Lee over London Avenue Canal  City Funded Planning AD City Park $0.00 TBD TBD Bridge reconstruction
DPW374 Royal St. (Canal - Esplanade)  PTP Complete C French Quarter $1,583,942.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW386 S Peters St (Canal - Calliope St)  PTP Construction C Central Business District $1,294,920.00 24-Mar-14 A Q3 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW441 S. Galvez St. (Jackson Ave. - Toledano) CDBG Funded Planning B Central City $6,000,000.00 Q2 2015 Q1 2016 Full reconstruction of concrete  roadway including all underground utilities. Installation of ADA compliant curb  ramps, new sidewalks, driveways, landscaping, street lights and striping of  crosswalks and a dedicated bike lane.
DPW264 S. Galvez Street ( Earhart- Toledano) Bikeway City Funded Design B Broadmoor $0.00 Q3 2014 Q3 2014 Install new pavement markings and  signage
DPW176 S. Jeff. Davis (M. L. King Jr. - Howard) City Funded Complete B Gert Town $2,093,866.67 10-Oct-11 A 30-Mar-12 A Reconstruction of existing roadway, including the  replacement of affected utilities.
DPW362 S. Jefferson Davis Pkwy (Gravier - Canal)  PTP Complete B Tulane - Gravier $1,036,904.00 06-Nov-13 A 12-Mar-14 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW406 S. Jefferson Davis Pkwy Bridge Ramp Repairs  PTP Construction B Gert Town $325,000.00 12-May-14 A Q3 2014 Removal  and replacement of the sidewalk intersections for the installation of the  compliant ADA ramps and the installation of the ADA ramps in the  medians.
DPW418 S. Tonti St. (Julia - Old Poydras) CDBG Funded Construction B Tulane - Gravier $36,905.00 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
PWF055 School Zone Flashing Beacons  City Funded Complete ABCDE City Wide $1,796,356.00 05-Aug-08 A 29-Nov-10 A Repair and/or replacement of damaged  school zone flashers with new solar-powered flashers
DPW412 Short (Washington - Palm) CDBG Funded Construction A Gert Town $99,961.25 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW187 St. Anthony Path Landscape (Mirabeau - Pelopidas)  CDBG Funded Complete CD Dillard $659,660.25 14-May-12 A 22-Jan-13 A An enhancement project that may include: Extending the median along St  Anthony Ave from Mirabeau Ave to Pelopidas Ave, wideing the median to  accommodate the new walking path, additional planting of trees along the walking  path from Pelopidas Ave to Gentilly Blvd, adding a walking path along St Anthony  Ave from Gentilly Blvd to Interstate 610.
DPW188 St. Bernard Ave Streetscape (N. Claiborne - North Miro St)  CDBG Funded Construction CD Seventh Ward $828,015.00 27-May-14 A Q3 2014 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW291 St. Bernard Ave. (Filmore Ave. to Robert E. Lee Blvd.) City Funded Bid & Award D Filmore $627,030.00 Q1 2015 Q2 2015 Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW189 St. Bernard Ave. (I-610 - Filmore Ave.)  PTP Complete D St. Bernard Area $3,228,389.00 20-Nov-09 A 02-May-11 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW348 St. Bernard Ave. (N. Rampart - Sere)  PTP Complete CD Seventh Ward $3,940,205.00 01-Jun-13 A 17-Oct-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW184 St. Charles Ave (Calliope St - Louisiana Ave) City Funded Design B Central City $800,000.00 Q2 2015 Q2 2016 Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW324 St. Charles Ave (Napoleon Ave. - Louisiana Ave) City Funded Design B Milan & Touro Neighborhoods $545,000.00 Q1 2016 Q1 2017 Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW190 St. Charles Ave (Nashville Ave - S. Carrollton Ave)  PTP Complete A Uptown $3,035,595.00 03-Aug-09 A 06-Oct-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW281 St. Charles Ave (Nashville Ave - S. Carrollton) Bikeway City Funded Complete A Audubon $30,752.70 28-Jan-13 A 01-Feb-13 A Install new pavement markings and  signage
DPW330 St. Charles Ave (S. Carrollton - Leake) & S. Carrollton (St Charles - Leake) Roadway Rehabilitation City Funded Complete A Audubon $74,030.00 17-May-10 A 10-Jun-10 A Asphalt  pavement, base repair and curb replacement.
DPW191 St. Charles Ave. (Canal St - US 90)  PTP Complete B Central Business District $958,678.00 03-Nov-09 A 10-Dec-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW383 St. Charles Ave: Streetscaping Improvements Ph 1 (Callipe - S. Carrollton) City Funded Planning A City Wide $0.00 Q3 2015 Q1 2016 May include sidewalk or other pedestrian walkway  improvements, bikeways, traffic and pedestrian signage or signalization,  landscaping, lighting, or public art.
DPW444 St. Claude Drainage Improvements CDBG Funded Planning C St. Claude $1,500,000.00 Q3 2015 Q2 2016 May include subsurface drainage improvements, installation of green infrastructure, 2 inch mill and  overlay and installation of ADA compliant curb ramps.
DPW375 St. Louis St. (Dauphine - Decatur)  PTP Complete C French Quarter $449,782.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW370 St. Louis St. (N Rampart - Dauphine)  PTP Complete C French Quarter $311,111.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW185 St. Roch and St. Claude Roadway Improvements (St. Claude Ave. - N. Roman St.)  CDBG Funded Complete CD St. Roch $787,341.80 11-Jan-10 A 01-Nov-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA ramps  including street name tiles.
DPW326 St. Roch/St.Claude Intersection Revitalization City Funded Complete C St. Roch $573,005.96 31-Jan-13 A 18-Mar-13 A May include sidewalk or other pedestrian walkway  improvements, bikeways, traffic and pedestrian signage or signalization,  landscaping, lighting, or public art.
DPW410 Stroelitz (Joliet - Dublin) CDBG Funded Construction A Gert Town $188,324.13 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW401 Sullen Pl (Gen DeGaulle - Patterson)  PTP Design C Old Aurora $2,595,700.00 Q4 2014 Q1 2015 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW423 Sumner (Lawrence - Newton) CDBG Funded Bid & Award C Behrman $700,655.85 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW422 Sumner (Mardi Gras - Lawrence) CDBG Funded Bid & Award C Whitney $105,851.00 Q3 2014 Q3 2014 Rehabilitation of concrete pavement  including panel patching/replacements, clearing and sealing of joints, crack  sealing and curb repair. Additional improvements include sidewalk repair,  construction of ADA ramps, installation of high-visibility crosswalks and other  roadway striping.
DPW195 Tchoupitoulas St (Canal St - Calliope St) City Funded Complete B Central Business District $1,893,227.84 20-Mar-12 A 30-Jun-12 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW376 Toulouse St. (Dauphine - Decatur)  PTP Complete C French Quarter $314,017.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW371 Toulouse St. (N Rampart - Dauphine)  PTP Complete C French Quarter $315,191.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW196 Tulane Ave and Jeff. Davis Pkwy Streetscape - Baudin St, Clark, and D'hemecourt CDBG Funded Complete B Mid-City $139,659.30 14-May-12 A 11-Nov-12 A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW341 Tupelo St. (Douglass St. - St. Claude Ave.)  PTP Complete E Lower Ninth Ward $338,763.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. 
DPW242 Urquhart St. (Elysian Fields Ave - Franklin Ave) City Funded Complete C St. Roch $4,617,169.99 14-Feb-11 A 11-Nov-11 A Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW426 Vespasian Blvd. (Lauradale - Wall Blvd.) CDBG Funded Bid & Award C Behrman $176,640.75 Q3 2014 Q3 2014 Rehabilitation of asphalt pavement including mill, patching, and 2-inch  overlay. Additional improvements include sidewalk repair, construction of ADA  ramps, installation of high-visibility crosswalks, and other roadway  striping.
DPW427 Vespasian Blvd. (Wall Blvd. - Cobblestone Ln.) CDBG Funded Bid & Award C Behrman $1,997,536.70 Q3 2014 Q3 2014 Rehabilitation of concrete pavement  including panel patching/replacements, clearing and sealing of joints, crack  sealing and curb repair. Additional improvements include sidewalk repair,  construction of ADA ramps, installation of high-visibility crosswalks and other  roadway striping.
DPW296 Veterans Admin. Medical Ctr Infrastructure Improvements (Canal, S Claiborne, Tulane, & S Rocheblave) CDBG Funded Complete B Central Business District $12,111,051.64 06-May-10 A 11-Oct-11 A Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW405 Veterans Administration-LSU Medical Center Infrastructure Improvements CDBG Funded Construction B Tulane - Gravier $13,447,529.00 03-Jun-14 A Q1 2015 An enhancement project that may include: New road striping, improved curbs,  gutters and sidewalks, improvements to drainage and catch basins, installation  of new landscaping and streetlights.
DPW201 Vienna (Corinne - Nighthart) City Funded Bid & Award E Read Blvd East $83,560.00 Q1 2016 Q2 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW265 Washington ( S. Broad - Carrollton Ave) Bikeway City Funded Complete B Broadmoor $36,000.00 22-Aug-13 A 16-Dec-13 A Install new pavement markings and  signage
DPW153 Washington Avenue Pedestrian Crossing (Washington Ave. - Drexel Drive - Xavier) City Funded Construction B Broadmoor $3,630,676.97 Q3 2014 Q2 2015 Evaluation of installing a pedestrian  bridge over Washington/Palmetto Canal near Xavier University.
DPW251 Whitney Ave & L.B. Landry (Mardi Gras Blvd - Patterson Dr) Bikeway City Funded Complete C Whitney $14,000.00 22-Aug-13 A 21-Oct-13 A Install new pavement markings and  signage
DPW211 Wisner  Bridge over I-610 City Funded Design A City Park $0.00 Q3 2015 Q4 2016 Bridge reconstruction
DPW256 Wisner Overlay ( Esplanade Ave - Robert E Lee) Bikeway City Funded Design A City Park $0.00 Q4 2014 Q4 2014 Install new pavement markings and  signage
DPW213 Wright Road (Chef Menteur Blvd - Dwyer Rd) City Funded Bid & Award E Read Blvd East $474,980.00 Q1 2016 Q3 2016 Removal of existing roadways and replace with new hot mix  asphalt or concrete roadways including new concrete curb and gutter bottom,  rehabilitation of water and drain lines, constructing driveways, sidewalks and  handicap ramps, and all work incidental to the project as shown on the plans or  as directed by the Engineer in the field.
DPW445 Youth Study Streets  (Encampment, Senate, Cadillic, Milton St.) CDBG Funded Planning D St. Bernard Area $1,350,000.00 Q3 2015 Q2 2016 May include underground  infrastructure improvments, roadway resurfacing and installation of  ADA compliant curb ramps, sidewalks and driveway arpons near the Youth Study Center.

 

 