News

October 22, 2021 | From City of New Orleans

Traffic Advisory: Six Month Closure on Octavia Between Freret and Clara Streets for Full-Depth Reconstruction

Octavia St.

 

NEW ORLEANS — Beginning on Monday, Oct. 25 at 7 a.m., weather permitting, City of New Orleans contractor, Command Construction Industries, will start construction on the $5.1M bond-funded Octavia (Freret - Claiborne) Full-Depth Reconstruction Project.

 

Crews will close Octavia Street between Clara and Freret streets for approximately six months to safely accommodate full reconstruction of the roadway. Public safety is our priority; residents along Octavia have been notified via a neighborhood canvass. 

New roadways, sidewalks and underground utilities (water, sewer and drainage) are expected to be complete by summer 2022.  In general, Command Construction Industries will be working from 7 a.m. to 5:30 p.m., Monday through Friday. Permission to work on weekends may also be granted, if necessary.

 

A pre-construction community meeting was held earlier this year; however, the start of the project was delayed to allow time to complete the permitting process with the Louisiana Department of Transportation and Development for use of a laydown area on South Claiborne Avenue near Octavia Street. View a copy of the presentation here.

 

Intersection closures will happen sequentially on Octavia Street at South Robertson Street, Magnolia Street and Clara Street. These intersections will remain open whenever possible to minimize the impact to residents. Once construction is complete between Freret and Clara streets and Octavia Street has been reopened, crews will close and begin full reconstruction between Clara Street and South Claiborne Avenue. 

 

Throughout construction, several water service interruptions will occur for test closures and waterline tie-ins to the existing water supply. A notice will be given to impacted residents 48-hours prior to any water service disruptions. Additionally, the contractor will be working with residents to assist with weekly trash collections on Fridays. If residents require reasonable accommodations during construction, they may call the RoadworkNOLA hotline at 504.658.ROAD (7623).   

 

Since May 2018, DPW has completed 99 projects with an estimated value of $282M.  Today, 69 projects are under construction with an estimated value of more than $600M.

 

Questions about this project or RoadworkNOLA should be directed to 504.658.ROAD (7623) or roadwork@nola.gov.

 

To better serve our residents with more timely communication, RoadworkNOLA is in the process of building our distribution list to provide important construction updates via text messaging.  To sign up, you can text ROADWORK to 77295 or go to ready.nola.gov/alerts to create a whole profile and select the “roadwork” alert list.

 

# # #